Apr 2026

Routine Electrical Maintenance : DC2 | 18 April 2026
Scheduled for April 18, 2026 at 7:00 PM – 7:00 PM
  • Planned
    April 18, 2026 at 7:00 PM
    Planned
    April 18, 2026 at 7:00 PM

    Dear RSAWEB Customer,

    Routine electrical maintenance will be taking place at the RSAWEB Data Centre in Bree Street on Saturday 18 April 2026.

    Please see change information below:

    Maintenance Notice Summary:
    Planned Start Date/Time: 18/04/2026 21:00 SAST
    Planned End date/Time: 19/04/2026 01:00 SAST
    Maintenance Window: 4 hour(s)
    Expected Impact: None
    Affected Services: None

    Impact:
    Customers can expect no impact from this maintenance due to redundant power solutions in place. Engineers are on standby should any issues arise from this routine maintenance

    Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Routine Voice Platform Maintenance | 16 April 2026
Scheduled for April 16, 2026 at 3:00 PM – 3:00 PM
  • Planned
    April 16, 2026 at 3:00 PM
    Planned
    April 16, 2026 at 3:00 PM

    Dear RSAWEB Customer,

    RSAWEB engineers will be conducting routine maintenance on our voice platform to improve the resilience of our voice services.

    Please see change information below:

    Maintenance Notice Summary:
    Planned Start Date/Time: 16/04/2026 17:00 SAST
    Planned End date/Time: 16/04/2026 19:00 SAST
    Maintenance Window: 2 hour(s)
    Expected Impact: None/Low
    Affected services: 3CX PBX Routing & VOIP Services

    Impact:
    Customers can expect no impact to services. Engineers are on standby should any issues arise from this maintenance.

    Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Emergency Power Maintenance : Waterfront Access Node | 14 April 2026
  • Completed
    April 14, 2026 at 4:00 AM
    Completed
    April 14, 2026 at 4:00 AM
    Maintenance has completed successfully
  • In progress
    April 14, 2026 at 3:00 AM
    In progress
    April 14, 2026 at 3:00 AM
    Maintenance is now in progress
  • Planned
    April 14, 2026 at 3:00 AM
    Planned
    April 14, 2026 at 3:00 AM

    Dear RSAWEB Customer,

    RSAWEB engineers will be conducting emergency hardware maintenance at the Waterfront access node to improve the resilience of the network.

    Please see change information below:

    Maintenance Notice Summary:
    Planned Start Date/Time: 14/04/2026 05:00 SAST
    Planned End date/Time: 14/04/2026 06:00 SAST
    Maintenance Window: 1 hour(s)
    Expected Impact: High
    Affected services: Waterfront Access Node Connectivity Services

    Impact:
    Customers can expect a brief dip in connectivity during the maintenance window.

    Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Node Outage : Standard Towers Node | 11 April 2026
  • Resolved
    Resolved

    Dear RSAWEB Customer,

    We are observing services for Standard Towers node have restored and are testing stable.

    We anticipate no further service disruptions.

    Regards,
    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Monitoring
    Monitoring

    Dear RSAWEB Customer,

    We are observing services for Standard Towers restored at the moment.

    Engineers are monitoring for stability.

    Regards,
    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Investigating
    Investigating

    Dear RSAWEB Customer,

    We are observing an issue affecting services at the Standard Towers node.

    Engineers are currently investigating.

    Kindly await further updates.

    Regards,

    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

Data Centre Backup Power System Load Test | 10 April 2026
  • Completed
    April 10, 2026 at 9:00 AM
    Completed
    April 10, 2026 at 9:00 AM
    Maintenance has completed successfully
  • In progress
    April 10, 2026 at 7:00 AM
    In progress
    April 10, 2026 at 7:00 AM
    Maintenance is now in progress
  • Planned
    April 10, 2026 at 7:00 AM
    Planned
    April 10, 2026 at 7:00 AM

    Dear RSAWEB Customer,

    RSAWEB Engineers will be conducting proactive, routine maintenance on the backup power system at the RSAWEB Data Centre. Routine testing of the data centre backup power system ensures it is operating at optimal performance

    A simulated power grid failure will be initiated to test seamless transfer to backup power, followed by load and failover testing of each of the backup generators.


    There is no impact to services expected as the power load can be diverted back to grid power at any time.

    Maintenance Window:

    Date: 10 April 2026

    Time: 09:00AM - 11:00PM

    Duration: 2 hours

    If you require any information regarding this maintenance please reach out to our support teams via 087 470 0500 or soc@rsaweb.net.

    Regards,
    RSAWEB Enterprise SOC Team

Mar 2026

Data Centre Backup Power System Load Test | 27 March 2026
  • Completed
    March 27, 2026 at 9:00 AM
    Completed
    March 27, 2026 at 9:00 AM
    Maintenance has completed successfully
  • In progress
    March 27, 2026 at 7:00 AM
    In progress
    March 27, 2026 at 7:00 AM
    Maintenance is now in progress
  • Planned
    March 27, 2026 at 7:00 AM
    Planned
    March 27, 2026 at 7:00 AM

    Dear RSAWEB Customer,

    RSAWEB Engineers will be conducting proactive, routine maintenance on the backup power system at the RSAWEB Data Centre. Routine testing of the data centre backup power system ensures it is operating at optimal performance, in light of the ongoing Eskom loadshedding, and the fragile state of the national power grid.

    A simulated power grid failure will be initiated to test seamless transfer to backup power, followed by load and failover testing of each of the backup generators.


    There is no impact to services expected as the power load can be diverted back to grid power at any time.

    Maintenance Window:

    Date: 27 March 2026

    Time: 09:00AM - 11:00PM

    Duration: 2 hours

    If you require any information regarding this maintenance please reach out to our support teams via 087 470 0500 or soc@rsaweb.net.

    Regards,
    RSAWEB Enterprise SOC Team

Service Disruption : RSAWEB Telephony Systems | 26 March 2026
  • Resolved
    Resolved

    Dear RSAWEB Customer,

    We are observing services for RSAWEB's Contact Centre have restored and are testing stable.

    We anticipate no further service disruptions.

    Regards,
    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Monitoring
    Monitoring

    Dear RSAWEB Customer,

    We are observing services for RSAWEB's Contact Centre have restored at the moment.

    Engineers are monitoring for stability.

    Regards,
    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Investigating
    Investigating

    Dear RSAWEB Customer,

    We are observing an issue affecting the RSAWEB Telephony System.

    This is not affecting managed 3CX services or customer VOIP lines, only RSAWEB's Contact Centre

    Engineers are currently investigating.

    Kindly await further updates.

    Regards,

    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

Scheduled Maintenance | JHB Teraco | 26 March 2026
  • Completed
    March 26, 2026 at 5:00 AM
    Completed
    March 26, 2026 at 5:00 AM
    Maintenance has completed successfully
  • In progress
    March 26, 2026 at 1:00 AM
    In progress
    March 26, 2026 at 1:00 AM
    Maintenance is now in progress
  • Planned
    March 26, 2026 at 1:00 AM
    Planned
    March 26, 2026 at 1:00 AM

    Dear RSAWEB Customer,

    RSAWEB engineers will be performing scheduled maintenance at our JHB Teraco POP as part of ongoing infrastructure optimization and resilience improvements within the core network environment.

    Please see change information below:

    Planned Start Date/Time: 26/03/2026 03:00 SAST
    Planned End date/Time: 26/03/2026 07:00 SAST
    Maintenance Window: 4 hours
    Expected Impact: Medium

    Impact:
    During this maintenance window, certain enterprise connectivity services may experience brief periods of interruption while adjustments are performed within the underlying network infrastructure.

    Our engineering team will be on standby throughout the activity to ensure the work is completed as efficiently as possible and to address any unforeseen issues should they arise. Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Routine Maintenance | Routing Fail-Over Testing | 25 March 2026
  • Completed
    March 25, 2026 at 3:00 AM
    Completed
    March 25, 2026 at 3:00 AM
    Maintenance has completed successfully
  • In progress
    March 25, 2026 at 1:00 AM
    In progress
    March 25, 2026 at 1:00 AM
    Maintenance is now in progress
  • Planned
    March 25, 2026 at 1:00 AM
    Planned
    March 25, 2026 at 1:00 AM

    Dear RSAWEB Customer,

    RSAWEB engineers will be conducting scheduled maintenance on environment to improve the resilience of the network.

    Please see change information below:

    Maintenance Notice Summary:
    Planned Start Date/Time: 25/03/2026 03:00SAST
    Planned End date/Time: 25/03/2026 05:00 SAST
    Maintenance Window: 2 hour(s)
    Expected Impact: Low
    Affected services: IPT

    Impact:
    Customers can expect no impact on services. Engineers are on Standby should a fault occur.

    Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Scheduled Maintenance | JHB Teraco POP | 24 March 2026
  • Completed
    March 24, 2026 at 5:00 AM
    Completed
    March 24, 2026 at 5:00 AM
    Maintenance has completed successfully
  • In progress
    March 24, 2026 at 1:00 AM
    In progress
    March 24, 2026 at 1:00 AM
    Maintenance is now in progress
  • Planned
    March 24, 2026 at 1:00 AM
    Planned
    March 24, 2026 at 1:00 AM

    Dear RSAWEB Customer,

    RSAWEB engineers will be performing scheduled maintenance at our JHB Teraco POP as part of ongoing infrastructure optimization and resilience improvements within the core network environment.

    Please see change information below:

    Maintenance Notice Summary:
    Planned Start Date/Time: 24/03/2026 03:00 SAST
    Planned End date/Time: 24/03/2026 07:00 SAST
    Maintenance Window: 4 hours 
    Expected Impact: Medium

    Impact:
    During this maintenance window, certain enterprise connectivity services may experience brief periods of interruption while adjustments are performed within the underlying network infrastructure.

    Our engineering team will be on standby throughout the activity to ensure the work is completed as efficiently as possible and to address any unforeseen issues should they arise. Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Feb 2026

RSAWEB Data Centre Backup Power System Load Test | 27 February 2026
  • Completed
    February 27, 2026 at 9:00 AM
    Completed
    February 27, 2026 at 9:00 AM
    Maintenance has completed successfully
  • In progress
    February 27, 2026 at 7:00 AM
    In progress
    February 27, 2026 at 7:00 AM
    Maintenance is now in progress
  • Planned
    February 27, 2026 at 7:00 AM
    Planned
    February 27, 2026 at 7:00 AM

    Dear RSAWEB Customer,

    RSAWEB Engineers will be conducting proactive, routine maintenance on the backup power system at the RSAWEB Data Centre. Routine testing of the data centre backup power system ensures it is operating at optimal performance, in light of the ongoing Eskom loadshedding, and the fragile state of the national power grid.

    A simulated power grid failure will be initiated to test seamless transfer to backup power, followed by load and failover testing of each of the backup generators.


    There is no impact to services expected as the power load can be diverted back to grid power at any time.

    Maintenance Window:

    Date: 27 February 2026

    Time: 09:00AM - 11:00AM

    Duration: 2 hours

    If you require any information regarding this maintenance please reach out to our support teams via 087 470 0500 or soc@rsaweb.net.

    Regards,
    RSAWEB Enterprise SOC Team

Scheduled Maintenance | Octotel CPT FTTx | 26 February 2026
  • Completed
    February 26, 2026 at 3:00 AM
    Completed
    February 26, 2026 at 3:00 AM
    Maintenance has completed successfully
  • In progress
    February 26, 2026 at 1:00 AM
    In progress
    February 26, 2026 at 1:00 AM
    Maintenance is now in progress
  • Planned
    February 26, 2026 at 1:00 AM
    Planned
    February 26, 2026 at 1:00 AM

    Dear RSAWEB Customer,

    RSAWEB engineers will be conducting scheduled maintenance on Octotel FTTx services in CPT to increase capacity and improve the resilience of the network.

    Please see change information below:

    Maintenance Notice Summary:
    Planned Start Date/Time: 26/02/2026 03:00 SAST
    Planned End date/Time: 26/02/2026 05:00 SAST
    Maintenance Window: 2 hour(s)
    Expected Impact: High
    Affected Services:

    • Octotel Kleinbrak

    • Octotel George

    • Octotel Wellington

    • Octotel Sea Point

    • Octotel Cape Gate

    • Octotel Strand

    • Octotel Athlone

    • Octotel Kensington

    • Octotel Bredasdorp

    • Octotel Moorreesburg

    Impact:
    Customers can expect intermittent to no connectivity for the duration of the maintenance window

    Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Node Outage : Multi-Flora Node | 24 February 2026
  • Resolved
    Resolved

    Dear RSAWEB Customer,

    We are observing services for Multiflora Node have restored and are testing stable.

    We anticipate no further service disruptions.

    Regards,
    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Investigating
    Investigating

    Dear RSAWEB Customer,

    We are observing an issue affecting services at the Multi-Flora node.

    Engineers are currently investigating.

    Kindly await further updates.

    Regards,

    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

Node Outage : Tokai Node | 24 February 2026
  • Resolved
    Resolved

    Dear RSAWEB Customer,

    We are observing services for Tokai Node have restored and are testing stable.

    We anticipate no further service disruptions.

    Regards,
    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Update
    Update

    Dear RSAWEB Customer,

    Partner provider technicians continue working on investigating and localizing the point of failure,

    Kindly await further updates.

    Regards,

    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Identified
    Identified

    Dear RSAWEB Customer,

    Partner provider technicians have identified a fibre break.
    Technicians are currently localizing the point of failure.

    Kindly await further updates.

    Regards,

    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Update
    Update

    Dear RSAWEB Customer,


    Partner provider technicians have been dispatched to further investigate.

    Currently no ETR is available.

    Kindly await further updates.

    Regards,

    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

  • Investigating
    Investigating

    Dear RSAWEB Customer,

    We are observing an issue affecting services at the Tokai node.

    Engineers are currently investigating.

    Kindly await further updates.

    Regards,

    RSAWEB NOC

    www.rsaweb.co.za | 087 470 0500

Scheduled Firmware Maintenance : FTTx, CPT & JHB | 24 February 2026
  • Completed
    February 24, 2026 at 3:00 AM
    Completed
    February 24, 2026 at 3:00 AM
    Maintenance has completed successfully
  • In progress
    February 24, 2026 at 1:00 AM
    In progress
    February 24, 2026 at 1:00 AM
    Maintenance is now in progress
  • Planned
    February 24, 2026 at 1:00 AM
    Planned
    February 24, 2026 at 1:00 AM

    Dear RSAWEB Customer,

    RSAWEB engineers will be conducting scheduled firmware maintenance on in CPT and JHB to increase capacity and improve the resilience of the network.

    Please see change information below:

    Maintenance Notice Summary:
    Planned Start Date/Time: 24/02/2026 03:00 SAST
    Planned End date/Time: 24/02/2026 05:00 SAST
    Maintenance Window: 2 hour(s)
    Expected Impact: High
    Affected Services:

    JHB FTTx

    • Evotel

    • Frogfoot

    • Link Africa

    • Vumatel

    • NetX

    • OpenFibre

    • MFN

    CPT FTTx

    • Octotel

      • Gugulethu

      • Green point

      • Blouberg

      • Mutual Heights

      • Rondebosch

      • Lakeside

      • Melkbos

      • Bree Street

      • Bellville

      • Athlone

      • Plettenberg Bay

      • Ruyterwacht

      • Knysna

      • Sedgefield

    Impact:
    Customers can expect intermittent to no connectivity for the duration of the maintenance window

    Our support teams are available on 087 470 0500 or soc@rsaweb.net for RSAWEB Business customers.

    Regards,
    RSAWEB NOC
    Network Operations Centre

Feb 2026 to Apr 2026

Next