RSAWEB Services - Frogfoot | Emergency Maintenance; Hardware Replacement | 8 January 2025 – Maintenance details

All systems operational

Frogfoot | Emergency Maintenance; Hardware Replacement | 8 January 2025

Completed
Scheduled for January 08, 2025 at 9:00 PM – January 09, 2025 at 5:00 AM

Affects

Core Connectivity Services

Under maintenance from 9:00 PM to 5:00 AM

Western Cape Connectivity Services

Under maintenance from 9:00 PM to 5:00 AM

Updates
  • Completed
    January 09, 2025 at 5:00 AM
    Completed
    January 09, 2025 at 5:00 AM
    Maintenance has completed successfully
  • In progress
    January 08, 2025 at 9:00 PM
    In progress
    January 08, 2025 at 9:00 PM
    Maintenance is now in progress
  • Planned
    January 08, 2025 at 9:00 PM
    Planned
    January 08, 2025 at 9:00 PM

    Dear RSAWEB Customer,

     

    Frogfoot engineers will be conducting emergency maintenance to replace faulty hardware.

     

    Please see the change information below:

     

    Maintenance Notice Summary:
    Planned Start Date/Time: 08/01/2025 23:00:00 SAST
    Planned End date/Time: 09/01/2025 07:00:00 SAST
    Maintenance Window: 8 hour(s) 
    Expected Impact: Medium 
    Affected services: Frogfoot FTTx Services

     

     

    Impact:
    Intermittent to no internet connection is anticipated during this window period for all subscribers within the Table View area.

     

    Regards,
    RSAWEB NOC
    Network Operations Centre